Basic requirements for the design of piping systems, central vacuum Vacuflo

 

1. Vertical section of the pipeline on which the rubbish and the dust is transported upwards, should not exceed 3 meters. In cases where dirt and dust must be raised higher than one floor, in the horizontal plane between floors pipe length should not be less than 2.4 meters

2. Connect the vertical segment of the pipeline to the horizontal main line is produced, either from above or from the side).

3. Tee (code 5515) should be used only in the horizontal plane; possible use other tees

4. All powertrains Vacuflo - single-phase, three-wire cable equipped for connection to a grounded electrical outlet that is installed within 1 meter of the installation location of the power unit. To power outlet should be positioned at the wire section of 2.5 square directly from the switchboard.

5. In order to maintain system stabilizer is recommended to provide for the installation of electric voltage. 6. The exhaust pipe length should not exceed 9 meters, taking into account losses in the bends.